Court Services Victoria
$894.7M
$894,726,307, 2026-27
Source: Victorian Budget 2026-27, Budget Paper No. 5, Court Services Victoria - Financial statement. Retrieved 25 September 2026.
Capital projects listed
11
From the published project register, largest first below.
Programs
This government publishes a total for the department but not what each of its programs costs, so there is no level below this one to show. The figure above is the one in the budget papers, and the projects and contracts below are the levels that are published.
Major projects
Courts case management system (statewide)
$98.4M
Estimated completion qtr 2 2026-27. The TEI has increased by $18.882 million, $16.812 million due to increased delivery complexity and $2.070 million reprioritised from the New federal jurisdiction matters in the Magistrates' Court of Victoria (Melbourne) initiative. The estimated completion date has been revised to quarter 2 2026-27 in line with a revised project schedule.
Statewide · Existing project
Source: Victorian Budget 2026-27, Budget Paper No. 4, 2026-27 State Capital Program. Retrieved 25 September 2026.
Specialist family violence integrated court (statewide)
$73.9M
Estimated completion qtr 2 2026-27. The estimated completion date has been revised to quarter 2 2026-27 in line with a revised project schedule for the Broadmeadows site. Construction of the Geelong and Melbourne sites achieved practical completion in quarter 2 2025-26.
Statewide · Existing project
Source: Victorian Budget 2026-27, Budget Paper No. 4, 2026-27 State Capital Program. Retrieved 25 September 2026.
Victorian Civil and Administrative Tribunal digital service transformation (statewide)
$29.0M
Estimated completion qtr 4 2026-27. The estimated completion date has been revised to quarter 4 2026-27 in line with a revised project schedule to deliver new requirements following the establishment of Rental Dispute Resolution Victoria.
Statewide · Existing project
Source: Victorian Budget 2026-27, Budget Paper No. 4, 2026-27 State Capital Program. Retrieved 25 September 2026.
Delivering serious consequences and keeping the community safe (metropolitan)
$25.9M
Estimated completion qtr 4 2026-27. The TEI includes $7.756 million announced in the 2025-26 Budget Update.
Metropolitan · New project
Source: Victorian Budget 2026-27, Budget Paper No. 4, 2026-27 State Capital Program. Retrieved 25 September 2026.
Keeping Courts Open (statewide)
$21.1M
Estimated completion qtr 4 2026-27. The estimated completion date has been revised to quarter 4 2026-27 in line with a revised project schedule and a development application to Heritage Victoria for the Supreme Court site.
Statewide · Existing project
Source: Victorian Budget 2026-27, Budget Paper No. 4, 2026-27 State Capital Program. Retrieved 25 September 2026.
Maintaining our court buildings (statewide)
$10.6M
Estimated completion qtr 4 2026-27.
Statewide · New project
Source: Victorian Budget 2026-27, Budget Paper No. 4, 2026-27 State Capital Program. Retrieved 25 September 2026.
Children’s Court of Victoria Clinic and Conference Centre (Melbourne)
$4.6M
Melbourne · Completed project
Source: Victorian Budget 2026-27, Budget Paper No. 4, 2026-27 State Capital Program. Retrieved 25 September 2026.
Supporting a safe and effective Youth Justice system (Parkville)
$3.2M
Estimated completion qtr 4 2026-27. The TEI has increased by $1.136 million reprioritised from the Children’s Court of Victoria Clinic and Conference Centre (Melbourne) initiative to support works at the Melbourne Children’s Court to enhance service delivery capability. The estimated completion date has been revised to quarter 4 2026-27 in line with a revised project schedule.
Parkville · Existing project
Source: Victorian Budget 2026-27, Budget Paper No. 4, 2026-27 State Capital Program. Retrieved 25 September 2026.
New federal jurisdiction matters in the Magistrates’ Court of Victoria (Melbourne)
$1.7M
Melbourne · Completed project
Source: Victorian Budget 2026-27, Budget Paper No. 4, 2026-27 State Capital Program. Retrieved 25 September 2026.
Meeting the requirements of the Bail Further Amendment Act 2025 (statewide)
$1.5M
Estimated completion qtr 4 2026-27.
Statewide · New project
Source: Victorian Budget 2026-27, Budget Paper No. 4, 2026-27 State Capital Program. Retrieved 25 September 2026.
Other capital expenditure
Not published
Estimated completion n.a.. Other capital expenditure includes minor projects and recurrent investment to maintain and upgrade the existing asset base being undertaken and funded by the Department.
Existing project
Source: Victorian Budget 2026-27, Budget Paper No. 4, 2026-27 State Capital Program. Retrieved 25 September 2026.
Largest contracts
Nothing published is linked to this entity. Rows are matched to an entity by the name the register uses, which does not always match the name in the budget papers; the unmatched ones are still in the full register.